Operating Guidelines Committee Meeting Minutes
April 16, 2002
Attendees: Bill Bailey, Donny
Browning, Judy Jennings, Larry Keegan, Teri Leffek, Hope Moorer, Doug Plachy,
Morgan Rees
Note:
All recommendations proposed in the February and March 2002 minutes were accepted by
consensus
decision by the SEG at its April meeting.
Peer Review
Doug Plachy responded to Patty McIntosh's question about
double-blind studies. Yes, double-blind studies can be used by the Corps however you would
have to know this at the beginning of the process. It would be difficult to do this now in
the process, especially since the authors of the various reports are known. Morgan
recalled the October 26, 2000 discussion of this committee wherein we reviewed the EPA
Peer Review Handbook. In this document, the EPA reaches the conclusion that peer review as
performed in an academic environment does not work in a government setting. Morgan also
commented the draft report on peer review previously prepared noted that peer review would
be considered on a case by case basis and those studies whose review through the usual
process was not considered sufficient would be considered for peer review.
SEG Role in Mitigation/Impacts Identification
Morgan wondered if discussing how to maximize the SEG's role
was an effective use of the committee's time as the likelihood of any recommendations of
the SEG being adopted are high, especially considering all recommendations to date have
been adopted. If the situation arises that a recommendation is not approved, then that
subject should be discussed and each SEG member will have to decide whether or not to
lobby for the recommendation.
Bill noted there are normally not any incremental documents
produced between the studies and the preparation of the EIS. Larry confirmed the SEG will
continue to be involved in the communication of information as the EIS is prepared. Morgan
noted the cooperating agencies will identify impacts and propose mitigation measures.
These agency findings will be discussed with the SEG as is noted in the project schedule.
The question then to be answered is whether the SEG participates in the planning process
itself or reacts/provides feedback to the information/input provided by the cooperating
agencies and the Corps.
Doug requested that a suite of mitigation options be developed
early on by the SEG. Morgan thought we have enough information to begin this process by
brainstorming. Because of the start-up time and learning curve involved in mitigation
evaluation, the sooner the better to start. Bill proposed someone/entity could solicit
mitigation ideas from the SEG for the various resources. Judy agreed this brainstorming
process is a good idea but how should it be facilitated? Larry proposed letting the SEG
decide the groundrules/guidelines for this process. Judy felt this committee should
provide a set of questions to guide the SEG's discussion of groundrules/guidelines. Larry
added we should also solicit the opinion of the SEG facilitator Ben Dysart.
Bill suggested the SEG begin its brainstorming in more generic
and broader categories such as the resources (i.e. wetlands, fisheries, dissolved oxygen,
etc.) as all issues/concerns should fall within one or more of these categories. Teri
requested that the Corps provide a list of resources and note which issues are addressed
under the various resource categories.
Additional questions/rules to be proposed include:
- Is this a one-time or continual process?
- How might it be modified at a later time?
- The participation of an agency does not limit it actions outside of the SEG.
- If an idea/recommendation is made, that does not mean it will be approved later in the
process.
Larry reiterated whatever this committee proposes
needs to be clearly stated. Bill clarified that whatever ideas/feedback is provided will
be used later in conjunction with the interagency responses during the evaluation of
mitigation alternatives. Any input from the SEG will be submitted to GPA who in turn will
forward it to the Corps, the process currently utilized.
Larry inquired as to whether this brainstorming
process could also serve as a screening mechanism for issues identified by the SEG that
require no action/studies. The committee decided to treat this as a separate item. Morgan
has no problem with leaving issues on the list for which no action will be taken as these
issues will still have to be addressed in the EIS. Larry responded that confirmation of
whether these issues are still of concern or not and require any action should be
addressed sooner than later to which Morgan agreed.
Morgan will discuss the topic of cooperating agency reports to
the SEG in the upcoming interagency meeting.
The possibility of committees handling mitigation was discussed.
Morgan mentioned a comment made at the April SEG meeting - mitigation is not included in
the mission statement of any of the committees. Maybe it is best to consider the role of
committees fulfilled when all studies have been identified and completed. Any further
actions/decisions, including mitigation, then revert to the SEG membership at large.
The committee confirmed the SEG should address
mitigation but in the capacity of giving input/feedback to status reports, etc. rather
than proactively participate in the mitigation planning process. The committee noted
reasons the SEG should not develop mitigation include the time, money and technical
expertise required as well as affirmation the SEG's role in the project is advisory in
nature.
Attached is the committee's recommendation re: mitigation.
Final Work Product
It was decided this topic is not time sensitive therefore it was tabled.
There are no further meetings scheduled at this time.

Regarding the identification of impacts/mitigation, the Operating Guidelines
Committee makes the following two recommendations:
1. The role of the SEG in the identification of impact and
mitigation measures is to provide input/feedback from information provided and produced by
cooperating agencies and the Corps. The SEG has neither the time, funds nor technical
expertise to identify impacts and develop its own mitigation package. This is in
accordance with the advisory nature of the organization.
2. This committee recommends that to begin the process of
providing input/feedback to the Corps that the SEG institute a brainstorming process
rather than establish a mitigation committee. Providing mitigation ideas early on in the
development of the EIS is helpful especially considering the start-up time and learning
curve involved in mitigation planning. This committee proposes the SEG determine the
groundrules/guidelines for a brainstorming process. To assist that effort, the following
are offered:
Questions:
- Will the brainstorming process be a one-time or continual effort?
- How might it be modified at a later point in the development of the EIS?
- Who/what entity should facilitate the brainstorming process?
Groundrules/Guidelines:
- The participation of any agency or its representatives does not limit its/their
actions outside of the SEG.
- Brainstorming consists of the solicitation of any idea for which the individual
submitting it should not be ridiculed/penalized in any manner.
- If an idea is offered, that does not mean it will be approved later in the
development of the EIS.
- The brainstorming should occur at the level of the SEG at large rather than the
committees to achieve the most inclusive participation and begin to develop a
"big-picture" perspective.
- Any ideas/input submitted from the SEG will be given to GPA to be forwarded to the
Corps, the communication chain currently utilized and established.
- The brainstorming process begin with more generic and broader categories such as
wetlands, dissolved oxygen, fisheries, etc. which are the resources involved. The SEG
would start with a list provided by the Corps subject to any modifications that SEG wishes
to make.The ideas/feedback will be used by the Corps during the preparation of the EIS in
conjunction with the information and recommendations provided by the cooperation agencies.
|